The new construction works of Mezaparks are ahead of the work schedule for about a month and a half

On Thursday, 11 April, officials and representatives of the media became acquainted with the construction works of the new bandstand of Mezaparks.

“At present, the construction of a monolithic concrete frame and external engineering nets will continue at the site. An average of 115 employees are working in three shifts every day. The entire zero cycle has been built and the construction of second floor structures has already been started. All iron-concrete constructions are planned to be set up this summer, but by the winter, we intend to complete most of the assembled works of the metal structures currently being produced in Hungary,” informed Valdis Koks, the project director of the PS “LNK, RERE”.